CONSTRUCTION PLANNING TOOL

Concrete Pour Resource Planner

Check whether available resources can return the next layer within the user-entered initial setting time.

v1.9 • Codal Layer Limits + Balanced Desktop
1

Geometry & Concrete

1–150 m
IS 457 Cl. 4.10.2: maximum 0.45 m for Vibrated Mass Concrete. No numerical minimum is specified in this clause; 0.01 m is only the UI control floor.
Conventional concrete only. Roller-Compacted Concrete (RCC) is not supported in this version.
Single user-entered governing value.
2

Batching Plant

Planning rule: engine uses the lower of actual observed sustainable capacity and 65% of rated capacity.

3

Concrete Transport

Maximum 10 km/h within project area.
4

Placement Arrangement

Enter only actual observed sustainable capacity per operating unit — never manufacturer's rated capacity.

5

Compaction

Enter actual observed sustainable compaction capacity per operating unit/group.